Q

How to recover if incremental backup fails

If somehow only Tuesday's backup did not run or failed, then can I use the whole week's backup to restore and recover the database? In this situation what would be the backup strategy?

I have an RMAN backup stratagy: Every Sunday a level 0 backup is performed and every Monday to Saturday incremental backups are performed. If somehow only Tuesday's backup did not run or failed, then can I use the whole week's backup to restore and recover the database? In this situation what would be the backup strategy? Thanks.
If Tuesday's incremental level 1 backup was missed for some reason, then you need not worry. Wednesday's incremental backup will pick up the changes from Monday. And if you should have a crash before that backup, the archived redo logs contain all of the changes. Missing an incremental level 1 or 2 backup is not a major problem.
This was last published in July 2007

Dig Deeper on Oracle database backup and recovery

PRO+

Content

Find more PRO+ content and other member only offers, here.

Have a question for an expert?

Please add a title for your question

Get answers from a TechTarget expert on whatever's puzzling you.

You will be able to add details on the next page.

Start the conversation

Send me notifications when other members comment.

By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Please create a username to comment.

-ADS BY GOOGLE

SearchDataManagement

SearchBusinessAnalytics

SearchSAP

SearchSQLServer

TheServerSide

SearchDataCenter

SearchContentManagement

SearchFinancialApplications

Close